A change order email has one job: get a written yes, with a price and a schedule effect, before the extra work starts. Every email below carries the same five items: what changed and why, the price, the effect on the schedule, the date you need an answer, and a line the client can copy back to approve. Copy the one that matches the situation, fill the brackets, and send it from the project manager to the person who can sign.

Why the email matters even when you have a formal form

On many commercial jobs the contract names a process for changes, often a written change order signed by the owner. The signed form is what binds the parties, so read your contract's change clause before you send anything and follow its notice period, since some contracts set a deadline for giving notice of a claim. The email is what comes first: it describes the change in words the client can read in a minute, it starts the clock on a decision, and it leaves a dated record of who said what. An email is not a substitute for the contract's form, so have your attorney review the notice wording you will rely on.

Money on added work is often lost the same way: the field crew does the work because the client's representative asked on site, the paperwork follows weeks later, and by then the client remembers the request as part of the original scope. Sending the email the same day, with a price, breaks that pattern. See the scope creep email for the version written to a services client, and a scope of work template to draw the original line clearly.

The five items every change order email carries

  1. The change in one sentence. What was added, removed or found, and the location on the drawings or the room name.
  2. The reason. Client request, field condition, drawing conflict or code requirement. Stay neutral; describe, do not blame.
  3. The price, split into labor, material, equipment and markup if the contract allows markup, with the total as a single number.
  4. The schedule effect, in calendar days or "no effect", and the activity it touches.
  5. The decision date and the approval line. Give a date, say what happens to the affected work if you do not have an answer by then, and give one sentence to copy back.

Email 1: the client asks for added work

Every figure and name in these emails is invented, so replace them with your own breakdown.

Use it when the owner or the owner's representative asks for something outside the scope. Both parties know each other from the job, so this is a message inside an existing relationship.

Subject line: Change order request 014: added data outlets, second floor tenant suite

Hi Bertrand,

Following your request on site Tuesday, we priced 12 added data outlets in the second floor tenant suite, Rooms 204 to 215. The price is $9,840: labor $5,200, material $3,110, lift rental $480 and our markup of $1,050. The added work needs two working days after the cable arrives, and it does not move the substantial completion date.

We need your answer by Friday, March 5, to keep the electrical rough-in on schedule. To approve, please reply "Approved, change order request 014, $9,840" and we will issue the formal change order for signature. We will not start the added work before we have that reply.

Lorne
Mirdale Builders

The last sentence matters most. It tells the client in writing that the work waits for the yes, which keeps the decision where it belongs.

Email 2: an unforeseen condition

This one is harder, because the client did not ask for the work and may dispute it. Photos and a neutral tone do more here than any adjective.

Subject line: Notice of concealed condition: buried conduit at gridline C-4

Hi Bertrand,

While trenching for the new water line this morning, our crew found an abandoned conduit bundle at gridline C-4, about 30 inches below grade, which is not shown on the civil drawings or the site survey. Photos are in the shared project folder, and we have stopped work in a 20 foot area around it.

We need direction on whether the conduit is live. If it is abandoned, removing it adds about three working days and, by our early estimate, $7,200. We will send a firm price within 48 hours of your confirmation. Please tell us today whether you want us to proceed with removal or hold while your engineer reviews. Work elsewhere on the site continues.

Lorne
Mirdale Builders

Two things to notice. It reports the condition the day it was found, which supports a notice requirement if the contract has one. It also asks a question that the client can answer in one line, and it keeps the rest of the crew busy so the delay is limited to what the condition actually caused.

Email 3: a conflict in the drawings

Drawing conflicts are often resolved through a request for information first. The change order email follows the answer.

Subject line: Change order request 019 following RFI 037, mechanical duct and beam at the corridor

Hi Bertrand,

The response to RFI 037 moves the supply duct below the steel beam in the corridor, which lowers the ceiling at that point by 4 inches. The change adds $4,380 to the mechanical subcontract and two working days. We have confirmed with the architect that the lowered ceiling is acceptable. Please reply by Wednesday, April 7, with "Approved, change order request 019, $4,380," or tell us if you want a different solution priced.

Lorne
Mirdale Builders

What to do when the client does not answer

  • Follow up in two business days with the same request number, and copy the person who signs for the owner if the contract names one.
  • Do not start the work and do not hide the delay. Write the affected activity into your next schedule update.
  • If the work is urgent for safety, do the minimum needed to make the area safe, write down exactly what you did and why, and price the rest as normal.
  • Track every request on one log with number, date sent, amount, date approved and date invoiced, because unapproved changes that never get billed are the quiet margin leak.

To reach the person who actually signs for the owner, finding the project manager on a construction project shows where the name appears in public records and on the job. For payment once the change order is signed, how to follow up on an unpaid invoice picks up the process.

Change orders protect the margin on the jobs you already have; the next owner or general contractor still has to come from somewhere. Rocketship finds them: Emma looks up the owners, developers and general contractor project teams you describe by title, industry and place, reads each company's website and writes the first email from your own Gmail, then follows up and books the meeting on your calendar. Begin with the 7-day free trial on every monthly plan, card required. The pricing page lists the plans, and Starter is $12 a month.