A turnaround is a planned shutdown of a refinery, chemical plant, mill or power plant for inspection, repair and upgrade, and the owner needs a lot of skilled labor for a short window. Contractors win that work by getting through the owner's safety prequalification, by showing a crew they can mobilize on the owner's dates, and by being known to the turnaround manager before the scope is frozen. Price matters, but it comes after the first two: an owner will not look at your rates if your safety paperwork does not pass.
Why owners prequalify, and what they ask for
For plants covered by OSHA's process safety management standard, 29 CFR 1910.119, the owner has a legal duty when it hires a contractor to do maintenance, repair, turnaround, major renovation or specialty work on or near a covered process. When selecting a contractor, the employer must obtain and evaluate information about the contract employer's safety performance and programs (paragraph (h)(2)(i)). It must also tell contractors about known fire, explosion and toxic release hazards, explain the emergency action plan, control entry to covered areas, periodically evaluate contractor performance and keep an injury and illness log for contract employees working in process areas. On the contractor's side, paragraph (h)(3) requires that each contract employee be trained in the work practices needed to do the job safely, that the training be documented with the worker, the date and how understanding was verified, and that the contractor report any unique hazards its work creates.
That is why a prequalification package is a gate and not a formality. Expect to supply:
- Your recordable incident rate and days-away rate for the last three years, with the hours behind them.
- Your experience modification rate from workers compensation, if your state uses one.
- Your written safety program, your drug and alcohol policy and your incident investigation process.
- Training records for the crafts you will send, and the permits and certifications each one holds.
- Insurance certificates at the limits in the owner's master service agreement.
- Some owners route this through a third-party contractor safety management service that collects the documents; ask which one a plant uses before you start.
The incident-rate math the owner is checking
The Bureau of Labor Statistics gives the formula: the number of injuries and illnesses times 200,000, divided by employee hours worked. The 200,000 stands for 100 full-time employees working 40 hours a week for 50 weeks. In BLS's own example, a company with 7 recordable cases over 400,000 hours has a rate of 3.5, and 3 cases involving days away, restriction or transfer give 1.5. Here is the same arithmetic on invented numbers for a turnaround contractor.
- Your crews worked 600,000 hours over the last twelve months, counting every craft and supervisor.
- Your OSHA 300 log shows 6 recordable cases.
- The rate is 6 times 200,000, divided by 600,000, which is 2.0.
- If 2 of the 6 involved days away, restriction or transfer, that rate is 2 times 200,000, divided by 600,000, about 0.67.
Compute your own, with hours that match the payroll records, and keep the working sheet. A small contractor's rate swings with a single case, so show three years together and explain every case in a sentence. An owner who sees a clear explanation reads it as management. Our page on selling to risk managers shows how an insurance-side reader thinks about the same numbers.
Who owns the shutdown at the plant
| Role | What they decide | How to reach them |
|---|---|---|
| Turnaround manager or turnaround planner | Scope, schedule and which contractors are invited for each work package | A short note with your craft capacity and safety summary, well ahead of the scope freeze |
| Maintenance manager | Standing contractors, the master service agreement list | The same note, plus an offer to do routine work first |
| Contracts or procurement | Prequalification, rates, insurance and terms | A complete package, delivered on request, with no gaps |
| Site safety or contractor safety coordinator | Whether you pass the safety review | Your safety program and records, offered before they ask |
| The turnaround general contractor | Subcontracts for specialty work | The same package, plus a one-page description of the scope you handle |
Owners often plan a turnaround long before it starts, so the contact you want is the person planning the next one, not the one that is running now. Ask when the next shutdown is scheduled and when work packages go out to bid. Our page on selling to oil and gas operators covers the owner side in that sector, and becoming a national account vendor as a regional firm covers the vendor-status paperwork that sits behind many master service agreements.
Win routine work first
- Offer to do a small job outside a shutdown: a repair, an inspection, a short outage on one unit. It lets the plant see your people on site and lets you complete one cycle of its safety process.
- Do that job with no safety incident and no schedule surprise, and write a one-page summary with the hours worked and the crew.
- Ask the maintenance manager to introduce you to the turnaround planner.
- Offer a defined work package for the next turnaround, with crew size, craft mix, tools and an estimate of the labor hours.
- Ask what the plant needs from you by when, and put the dates in your calendar.
Writing to the planner before the scope freezes
Subject: A pipefitting and welding crew for your spring shutdown
Hi Marcela, I understand your site is planning its next major shutdown this spring. Stannard Industrial Services supplies pipefitters, certified welders and a safety lead for turnaround work at Gulf Coast refineries and chemical plants. If it would help, I can send our safety performance summary and a crew plan for the work packages you are still staffing. Who handles contractor prequalification for the shutdown, you or the site safety group?
Gideon
Stannard Industrial Services, [street address, city, state, ZIP]
If you would rather not get emails from me, reply "stop" and I will remove you.
The email gives a plain description of what you supply and offers two documents the plant needs anyway, and it asks who handles prequalification. It claims no safety record, and it should say "certified welders" only if every welder you send holds the certification. If your numbers are good, put them in the summary you send on request, with the hours behind them.
Numbers to keep by plant
- Plants where you have a complete prequalification on file and its expiry date.
- Planners and maintenance managers you have spoken to, by plant.
- Work packages you have been invited to bid and the dates.
- The share of your available craft hours committed for the next twelve months.
The research that precedes the safety paperwork is naming the planner and the safety coordinator at each plant. Rocketship can handle the list and the first emails: Emma reads each company's website, writes from your own Gmail, follows up and books the calls. Start with the plants in one region during a 7-day free trial on every monthly plan, card required, well before the next outage season; plans are on the pricing page.