Millwrights move, align and install machinery in plants and on industrial job sites, and rigging crews lift it into place. The work is sold against a calendar that the plant does not control: a planned outage, a shutdown window or a delivery date for a new machine. A crew that wins this work shows up with the rigging plan, the inspection records and the outage plan already written, because the plant's maintenance manager has to justify every hour of downtime.
Work the outage calendar
Plants schedule major maintenance in outages, which are planned shutdowns of a line or a whole site. The outage date is set months in advance, and the list of jobs inside it is set just before. A millwright crew that learns the outage date early can offer to take a job off the maintenance manager's list, and one that learns it late competes on price for whatever remains. The first question to ask a plant contact is when the next outage starts and how long it is planned to run. For another trade that sells into a building's fixed maintenance calendar, see how to get commercial HVAC contracts.
Outage work is also where much of the danger is, because crews work in tight spaces, around energized equipment and under cranes, all in a compressed time. The plant will look closely at the crew's safety file before it invites a bid for that work.
| Buyer | What the buyer is planning | What to offer |
|---|---|---|
| Plant maintenance manager | The outage job list and the hours per job | A fixed-hour estimate for the moves you can take, with a standby rate |
| Plant engineer | Alignment tolerances, the move path and the foundation | The alignment method and the record you will keep |
| Contractor project manager | A machinery install inside a larger job | A crew and lift plan that fits the schedule the prime sets |
| Safety manager | Whether the crew can work in the plant under its rules | The rigging inspection records and training files |
The rigging inspection rule
OSHA's rule for rigging equipment used in material handling is short and strict. Under 29 CFR 1926.251(a)(1), rigging equipment "shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe", and "defective rigging equipment shall be removed from service." Paragraph (a)(2)(ii) says rigging must not be "loaded in excess of its recommended safe working load as prescribed on the identification markings by the manufacturer."
The rule has two practical effects for a crew. The inspection is a shift-by-shift check, not an annual one, so the crew needs a form that records it. And the safe working load is the manufacturer's figure on the tag, so the crew cannot pick a sling by feel or use a rating from a different product. A plant safety manager will ask to see both.
What belongs in a rigging plan
- Lift list. Each machine or component, its weight from the drawing, and the center of gravity if known.
- Equipment. Each sling, shackle, beam and crane, with the rated capacity from the manufacturer's tag.
- Path. The route the load takes, the openings it passes through, and the clearance at each point.
- Crew and roles. The rigger, the signal person, the crane operator and the lead, with their training records.
- Inspection record. A blank shift inspection form that matches the rule, and the name of the person who signs it.
- Stop rule. Who can halt a lift and how the crew restarts it.
A plan that lists these six items is one a safety manager can check in a meeting. A plan that says "the crew will rig the machine safely" is not.
A worked move with invented numbers
Take an invented move. A food plant needs a 14,000-pound mixer moved 60 feet through a mezzanine opening during a planned four-day outage. A millwright crew of four quotes 22 hours for the rig and move at an invented rate of $95 an hour for the crew, plus $1,850 for a mobile crane for one shift. The quote totals $3,940 for the labor and crane, before the plant's own standby charges. The plant's maintenance manager asks for a standby rate of $120 an hour in case the crane is delayed past the window. The crew agrees, because the rig plan shows the lift is ready and the delay risk sits with the crane.
The numbers are an example, not a benchmark. The point is that the quote breaks into the parts the plant checks: crew hours, crane, and standby, each with its own line, and each tied to the rig plan.
Writing to the plant before the job list closes
A cold email to a maintenance manager should name the outage or the machine the plant has mentioned publicly, and ask one question about the schedule. The example below is from a fictional sender, Hector, at a fictional millwright company, Ferrand Millwright, to a first name at a plant. It carries the opt-out and the sender's address line, as the CAN-SPAM Act requires for commercial email.
Subject: Crew for the mixer move during your next outage
Hi Renata, the plant's last outage notice mentioned a mixer replacement on the mezzanine. Ferrand Millwright can take the rig and move with a four-person crew, a written lift plan and the inspection records your safety team asks for. When is the outage job list due to the contractors?
Hector, Ferrand Millwright, [street address, city, state, ZIP]
If you would rather not get emails from me, reply "stop" and I will remove you.
The email names a public notice and asks for a date. It offers a specific package without claiming the crew has never had an incident, and it does not promise a shutdown finish date.
What to show the safety manager
- The rigging inspection form, filled in with the last month's dates and a note of any equipment removed from service.
- Training records for each rigger and signal person.
- Certificates of insurance that name the plant as required by its contract.
- The incident history for the last three years, with the corrective action for each.
Send the file before the job list is set, not after the bid is awarded. A plant that has the file on its desk can add a crew to the outage without a second round of questions.
For the contractor side of a large install, see how to get data center construction subcontracts, which covers the prequalification steps a prime asks for. For a service crew that wins work through a general contractor, how to get clients as a general contractor shows the same buyer from the other side.
The crew that shows the lift plan first is the one a maintenance manager remembers. Rocketship puts that plan in front of more plants: Emma finds the maintenance and project managers you name, sends the lift plan offer from your own Gmail, follows up and books the site walk on your calendar. Starter is $12 a month on the pricing page, and a 7-day free trial on every monthly plan, card required, lets you reach the first plants before the next outage.