A liquidated damages clause sets a fixed amount, often a daily sum, that a contractor pays if the work finishes late, without the owner having to prove its actual loss. In the standard legal definition, liquidated damages are an exact amount of money, or a set formula for calculating it, written into the contract before it is signed, and courts decline to enforce a clause that is punitive, illegal, unconscionable or contrary to public policy. A contractor negotiates three things: the daily rate, a cap on the total, and the events that stop the clock. The cap and the excused delays often matter more than the rate.

What the federal construction clause looks like

Federal construction contracts use a standard clause. FAR 52.211-12, titled "Liquidated Damages-Construction," provides that if the contractor fails to complete the work within the time the contract specifies, the contractor pays a fixed daily sum for each day of delay until the work is finished or accepted. The contracting officer fills in the amount. Private contracts are not bound by that clause, but it is a useful model because it shows the basic structure: a time, a daily amount and an end point.

A private owner's form may look different. It may use a percentage of the contract price per week, a flat sum per milestone or a formula tied to the owner's own costs. Read the form for the same three parts before you sign: when the clock starts, what amount applies per day or per week, and when the damages stop.

Then ask whether the amount is a fair estimate. For sales of goods, UCC 2-718(1) allows damages to be liquidated only at an amount that is reasonable in light of the anticipated or actual harm, and it treats an unreasonably large figure as a void penalty. A construction contract is judged under the contract law of the state that governs it, and a court there can ask a similar question about the rate, so keep the owner's own reasons for its daily figure in the file: they are the best evidence that the rate is compensation, not punishment.

Cap math on an invented $2,000,000 contract

The figures below are invented. A subcontractor signs a $2,000,000 contract with a daily liquidated damages rate of $1,200 and a cap of 3 percent of the contract price.

  1. The cap is 3 percent of $2,000,000, which is $60,000.
  2. At $1,200 a day, the cap is reached after 50 days, because $60,000 divided by $1,200 is 50.
  3. If the work finishes 30 days late, the damages are 30 times $1,200, or $36,000.
  4. If the work finishes 60 days late, the damages without a cap would be 60 times $1,200, or $72,000. With the cap, they stop at $60,000.

The example shows why the cap matters. Without it, the 60-day delay would cost $72,000, and the contractor would have no defined maximum to price into the bid.

Five terms worth asking for

  • A cap on the total, stated as a dollar figure or a percentage of the price, and set before the schedule is agreed.
  • A start date that matches the notice to proceed, not the date the contract was signed, so the clock does not run while the site is closed.
  • Excused delays for events outside the contractor's control, such as severe weather, the owner's late approvals and differing site conditions, with a written notice process for each.
  • A rule that the damages are the owner's only remedy for delay, so the owner cannot add its actual losses on top.
  • A rule that the damages stop when the work is substantially complete, rather than when the last punch item is closed.

Each term is a separate negotiation. An owner may accept the cap and refuse the excused delays, or accept the notice process and resist the sole-remedy rule. Trade them in writing, and keep the schedule the contract assumes in the same document.

Schedule risk before the signature

A contractor should compare the daily rate with the schedule it can really keep. If the rate is more than the contractor earns on the job each day, a small delay can wipe out the margin. Build the schedule with the weather days and the inspection waits that the trade often sees, and check the liquidated damages against that schedule rather than the owner's best case.

Take the invented job below as a test. Its planned margin is $160,000 over a 200-day schedule, which works out to $800 of margin a day ($160,000 divided by 200). A $1,200 daily rate is larger than that $800, so each day of delay costs more than the job earns on a normal day, and the contractor would be paying to keep working. That is the case to put to the owner: either the rate comes down, or the cap is low enough that the exposure stays under the margin.

When a delay starts, the email to a client about a project delay gives wording for each cause, and the change order email for a commercial project shows how to put added work, and the time it needs, in writing. How to get masonry contracts covers the bid lists and prequalification a trade contractor faces before it signs.

What to put in writing before you sign

  1. The daily or weekly amount, the cap and the formula that produces the total.
  2. The clock start and the end point, with the actual dates the contract uses.
  3. Each excused-delay event, the notice it needs and the deadline for that notice.
  4. A statement of whether the damages are the only remedy for delay.
  5. A one-page schedule showing where the risk sits, signed by the person who approves the bid.

Owners and general contractors who sign fair delay terms are worth finding before the bid, and Rocketship's Emma finds the ones you describe, writes to them from your Gmail and answers their replies. Pricing starts with Starter at $12 a month on the pricing page, and the 7-day free trial on every monthly plan, card required, lets you see which owners reply before you bid.