Use this checklist when a bid invitation or RFP arrives and your estimators have limited days. Score eight questions from 0 to 5, multiply by the weights, and add the total. A total of 70 or more out of 100 is a bid, 50 or less is a no bid, and the middle needs a person to decide in writing and say why. The weights and cut-offs below are a starting point to adjust with your own history; the discipline of scoring every opportunity the same way is what matters.
Why the decision needs a number
An estimator's week is the most limited resource in a bidding firm. A complex bid can take several days of takeoff, vendor quotes and review, and a lost bid returns nothing for that time. Firms that bid everything often win the jobs nobody else wanted at a price that leaves no margin, and firms that decide by gut feel can keep bidding for owners who have already chosen someone else. A short, written score makes the decision comparable from one bid to the next, and it gives you data: after a year you can see which scores turned into wins.
The eight questions
| Question | Weight | Score 5 means | Score 0 means |
|---|---|---|---|
| 1. Do we know the owner or the general contractor, and do they know us? | 3 | Repeat customer who has paid on time | Never heard of them |
| 2. Does the scope match work we have done well? | 3 | Same type and size as three recent jobs | New type of work, no references |
| 3. How many firms are bidding, and are we invited or competing in an open field? | 2 | Invited, three or fewer bidders | Open bid, many bidders |
| 4. Is the schedule realistic with our crews? | 2 | Crews free in the window | Window overlaps our busiest months |
| 5. Are the contract terms acceptable (payment, retainage, liquidated damages, change order clause)? | 3 | Terms we have signed before | Pay-when-paid with long delays, heavy penalties |
| 6. Is the documentation complete (drawings, specs, addenda)? | 1 | Complete set, time to ask questions | Missing sheets, bid due in days |
| 7. What does it cost us to bid, in estimator days? | 2 | Under one day | More than five days |
| 8. Is the margin worth the risk (size of job against our bonding and cash)? | 4 | Expected margin at or above target, cash flow safe | Would strain bonding or cash |
The weights sum to 20, so the maximum is 100 points (each question scored 0 to 5, multiplied by its weight). Seventy points or more is a bid, 50 or fewer is a no bid, and 51 to 69 goes to the owner of the firm for a decision, with a written reason. Raise the weight on the questions that have cost you most in the past; if a poor contract clause has hurt you before, the weight on question 5 should be higher.
A worked example: two bids scored
Wrenlow Mechanical, an invented firm, receives two invitations in one week.
| Question (weight) | Clinic renovation, repeat customer | Open bid, new school wing |
|---|---|---|
| 1 Know the customer (3) | 5 = 15 | 1 = 3 |
| 2 Matches our work (3) | 4 = 12 | 3 = 9 |
| 3 Number of bidders (2) | 4 = 8 | 1 = 2 |
| 4 Schedule fits crews (2) | 4 = 8 | 2 = 4 |
| 5 Contract terms (3) | 4 = 12 | 2 = 6 |
| 6 Documents complete (1) | 4 = 4 | 3 = 3 |
| 7 Cost to bid (2) | 4 = 8 | 1 = 2 |
| 8 Margin against risk (4) | 4 = 16 | 2 = 8 |
| Total | 83 | 37 |
The clinic job scores 83 and gets your most experienced estimator. The school wing scores 37 and is a no bid. Writing the totals down takes ten minutes and replaces a long argument.
Declining without losing the customer
A no bid on an invitation from a general contractor you work with should be a short email, sent before the bid deadline, with a reason that is true. The recipient already knows you, so this is a business message between people who have worked together.
Subject line: No bid on the east wing mechanical package for Kelvane Construction
Hi Walt,
Thank you for the invitation on the east wing mechanical package. We are not going to bid it. The schedule overlaps two projects our crews are committed to, and I would not give you a number I could not stand behind. We would like to be on your list for the next package, and the summer renovation you mentioned fits our work well. Please keep us in mind.
Gina
Wrenlow Mechanical
General contractors keep a list of subs who answer, and a polite no keeps you on it. See how to get on general contractor bid lists for what keeps you there, and how to respond to an RFP as a small firm when the answer is yes. Once a bid is submitted, the follow-up email after a bid submission covers the next step.
Review the scores every quarter
- List every bid and its score. Mark the ones you won.
- Look at the average score of the wins against the losses. If wins cluster above 75, move the bid line to 75.
- For each loss with a high score, read why you lost. If it was price, check question 8; if it was relationship, check question 1.
- Check how many no bids later turned out to be easy jobs for the winner. That tells you whether you are too strict.
The checklist decides which bids to chase; the invitation list decides how many you get to score. Rocketship works on the second number: Emma finds general contractors, owners and facility managers by title, industry and place, reads each company's website and asks for a place on their bid list in an email from your own Gmail. Start with three general contractors you have never bid for, during a 7-day free trial on every monthly plan, card required; Starter is $12 a month on the pricing page.